All 16 North Carolina state parks affected by Hurricane Helene have reopened at least in part, but officials say more than $70 million separates the money received so far from the projected cost of completing repairs. Brian Strong, director of the N.C. Division of Parks and Recreation, told the Governor’s Advisory Committee on Western North Carolina Recovery that the state has received $41.3 million from federal, state and insurance sources. The division projects the work will cost $111.9 million.
“All of the parks are back open again, which is the great news,” Strong said during the committee’s Nov. 16 meeting at Lake James State Park. “They’re all open, but not every location in every park is open.”
The state’s presentation showed 301 of 315 miles of affected trails have been cleared and reopened. None of the 11 damaged bridges has received a permanent repair, although a temporary bridge has restored access to Chimney Rock State Park. The largest cost disparity involves a permanent bridge serving Chimney Rock. Strong said about $3 million was initially obligated for the project, while the N.C. Department of Transportation’s current estimate is about $52 million.
Strong said the higher estimate reflects a much larger and more resilient project than the bridge Helene destroyed. Plans call for combining the former Southside Drive bridge and the state park access bridge into one structure running from a roundabout in Chimney Rock Village across the Broad River.
“The bridge will be longer. It’ll be wider,” Strong said. “The idea is the engineering of that would be greater to ensure that the next flood event, it’s not going to end up being destroyed like it was.”
NCDOT is completing its cost estimate before the state returns to the Federal Emergency Management Agency with updated figures, Strong said. Federal and state transportation officials have said the combined bridge would improve access to both the park and Southside Drive. The funding received to date includes $19.9 million from FEMA, $2.1 million from N.C. Emergency Management, about $485,000 in insurance proceeds and $18.8 million from the Parks and Recreation Trust Fund. FEMA has obligated $26.9 million, while N.C. Emergency Management has obligated $2.7 million.
Strong said the parks division redirected about $9 million from previously funded trust-fund projects to begin storm repairs, delaying some other work. As FEMA reimbursements arrive, the division is putting money back into those projects. Helene also added roughly 40 projects to the workload of the division’s maintenance and capital staff, he said.
“Back and forth with FEMA on pricing and estimates has kind of delayed those projects, pushed back some of those start dates,” Strong said. “I think we as an organization are getting a little frustrated, but I think the public also is a little frustrated” about continued closures at favorite trails and recreation areas.
Seven sites have FEMA projects with projected costs exceeding $1 million: Elk Knob, Grandfather Mountain, Lake James, South Mountains, Pisgah View and Chimney Rock state parks, along with Yellow Mountain State Natural Area. At Lake James, where the committee met, the swim beach is operating after sand replacement and other repairs. Officials said work remains on a picnic area, damaged sediment ponds and culverts. One mountain biking trail remains closed.
Temporary repairs have also made the park’s docks usable, but officials said the docks and piers eventually need complete replacement. They described the repairs as a way to provide interim access while permanent work moves forward. Other progress includes reopening the upper portion of Grandfather Mountain State Park’s Profile Trail, repairing a well house at New River State Park and completing road repairs within Mount Mitchell State Park. Debris removal is complete at affected parks except along a 26-mile state-managed section of the New River, where officials are working through environmental requirements for the wild and scenic river.
Several prominent attractions remain limited. The lower section of the Profile Trail was largely washed away and will require a reroute and new bridges. High Shoals Falls-area trails at South Mountains remain closed while engineering work continues. Strong said Chimney Rock visitation remains about 50% below its previous level as the village continues rebuilding. The Blue Ridge Parkway’s continued closure near Mount Mitchell has also reduced traffic to that park. Strong said the contractor operating the Mount Mitchell restaurant closed early for the season because revenue was too low to remain open.
The lingering closures carry economic consequences beyond the parks. Amy Allison, director of the N.C. Outdoor Economy Office, told the committee that outdoor recreation generated $17.8 billion in economic activity in North Carolina in 2024, supported more than 155,000 jobs and accounted for 2.1% of the state’s gross domestic product.State officials said full restoration will depend on completing negotiations, engineering and construction for the larger projects — work that will continue long after visitors see the gates reopen.